Tilley Road extension project
Tilley Road extension at Manly West is part of Lord Mayor Graham Quirk’s commitment to create a better Brisbane by investing $1.4 billion in 2012/2013 to tackle traffic congestion and make the city’s roads safer. This investment will also create jobs and keep our economy growing.
Summary
| Address | Tilley Road, between Old Cleveland Road and the Port of Brisbane Motorway (to be undertaken in 5 stages) |
| Ward | Doboy Ward |
| Project outcome | The project will reduce traffic congestion and improve the safety for all road users in the Manly West, Wynnum West, Wakerley and Chandler areas. |
| Latest update | Construction of Tilley Road extension stage 1 is now complete. Detailed design of Stage 2 has started and is expected to be completed mid 2013. |
About the project
The Tilley Road extension is a five stage project which will ultimately see the Port of Brisbane Motorway linked to Old Cleveland Road through a single direct north-south connection. The overall Tilley Road extension will connect Tilley Road, Wakerley with the Port of Brisbane Motorway, Hemmant.
Stage 1 of the Tilley Road extension involved construction of Kianawah Road South connecting Hargreaves Road to Wondall Road, and was completed in 2011.
Detailed design is now underway for Stage 2 of the Tilley Road extension. This stage involves connecting the intersection of Wynnum Road and Kianawah Road with the intersection of Wondall Road and Kianawah Road South via a one kilometre, four lane road.
Planned Future stages of the Tilley Road extension (timings to be confirmed):
Stage 3: Upgrading Kianawah Road through to Lindum Road to a four lane arterial road
Stage 4: Construction of a new arterial road in dedicated road reserve between Manly Road and the intersection of New Cleveland Road and Tilley Road
Stage 5: Upgrading of Tilley Road from the New Cleveland Road intersection through to Old Cleveland Road to a four lane arterial road.
Project Status
Preliminary design for Stage 2 was completed last year. Funding has been allocated for the 2012/2013 financial year to complete Stage 2 detailed design.
Funding for further stages of this project has not yet been allocated. Therefore, timing and detailed plans of these stages is unknown. Once funding has been allocated, Council will conduct consultation with directly affected landowners, residents and stakeholders during the design and construction phases of the project.
Benefits
Once the entire five stages of the Tilley Road extension are complete it will:
- provide a continuous link between Port of Brisbane and Old Cleveland Road
- relieve traffic congestion, increase connectivity and improve road safety in Manly West, Wynnum West, Wakerley and Chandler areas
More information
If you would like to provide comments, ask questions or find out more about the Tilley Road extension traffic improvements project, you can:
- phone the project information line on 1800 669 416
- phone Council on 07 3403 8888
- email the project team
- write to:
Tilley Road extension project
City Projects Office
Brisbane City Council
GPO Box 1434
Brisbane Qld 4001