A budget must support your application for a Building Stronger Communities grant. Use this page to access budget tips and view the budget table example to help you develop your budget.

Budget tips

  • Make sure your total project income equals your total expenditure.
  • Volunteer staff can be costed from $35 per hour for non-skilled labour and at relevant rates for professionals.
  • Provide a minimum of two recent quotes for all items detailed in the budget.
  • All quotes should be itemised and detail the full scope of works.
  • Ensure you are familiar with the program guidelines, in particular, what is eligible for funding.
  • If you include 'in-kind' contributions in your budget, provide a breakdown of your calculations and all relevant details for each item.
  • An accredited building certifier must be engaged for all capital works projects, to review plans before work commences, and to formally certify that the completed works have achieved compliance with the Building Code of Australia and the Disability Discrimination Act. The cost of engaging a certifier can be included in the project budget.

Please note that for the purpose of assessment:

  • All budget figures must be goods and service tax (GST) exclusive i.e. deduct GST from quotes and invoices.
  • If your organisation is not GST registered, 10% GST is added to your grant prior to assessment, but is not itemised as GST.
  • If your organisation is GST registered, 10% GST is added to your grant as an itemised GST gross-up.

An example budget table for the Building Stronger Communities Grant Program is below:

Income (source of funding) Amount (ex GST) Project expenditure (description of work and name of supplier) Amount (ex GST)
Brisbane City Council Building Stronger Communities Grant Program $100,000.00 Field works by <company name> $65,000.00
Organisation's financial contribution to the project $20,000.00 Irrigation system and installation $50,000.00
Organisation's 'in-kind' contribution to the project $15,000.00 Rain tanks $15,000.00
Other grants e.g. State Government Grant (approved) $25,000.00 Pump system $20,000.00
Other income

$0.00

$0.00

$0.00

Contingency 5%

Development Assessment and Building Approval costs (if applicable)

Accredited building certifier

$7500.00

$2000.00

$500.00

TOTAL INCOME $160,000.00 TOTAL EXPENDITURE $160,000.00

NOTE: Ensure all income and expenditure totals match.