Beenleigh Road and Nursery Avenue black spot project - Runcorn

Council is planning works at the intersection of the Beenleigh Road and Nursery Avenue intersection in Runcorn to improve safety for all road users as part of the 2019-20 Australian Government's Black Spot Program.

Project summary

This table includes project information for the Beenleigh Road and Nursery Avenue black spot project including address, ward, project outcomes and latest update.
Address Beenleigh Road and Nursery Avenue, Runcorn
Ward Runcorn
Project outcomes Improved safety
Latest update Project introduction

About the project

The intersection has experienced a relatively high crash rates, with eight reported crashes at the intersection between January 2013 and December 2018. The crashes resulted in one fatality, two hospitalisations and five incidents requiring medical treatment. The majority of these accidents resulted from right-turn movements from Nursery Avenue into Beenleigh Road.

The Black Spot Program is part of the Australian Government's commitment to reduce crashes on Australian roads. The program aims to improve road safety by implementing upgrade measures such as roundabouts and traffic signals appropriate to each black spot location.

Project features

The project involves:

  • signalising the intersection of Beenleigh Road and Nursery Avenue including pedestrian facilities
  • providing a dedicating right-turn signal into Nursery Avenue from Beenleigh Road for eastbound traffic
  • providing a dedicated left-turn lane into Nursery Avenue from Beenleigh Road for westbound traffic
  • converting the eastern end of the Beenleigh Road service road into a cul-de-sac
  • installing new access point in and out of the service road on Beenleigh Road
  • permitting a U-turn movement at the existing signalised intersection of Beenleigh road and Bonemill Road
  • providing new on-road cycle lanes on Beenleigh Road through the intersection
  • installing new pedestrian paths
  • tree removal and landscaping.

View the project documents in your preferred format:

Beenleigh Road service road access changes

To accommodate the signalisation of the intersection and ensure the safety of all road users, the eastern end of the Beenleigh Road service road will be converted into a cul-de-sac. However, a new access point, mid-way between Nursery Avenue and Datura Street, will be constructed as part of the project. In addition, a new U-turn movement will be permitted at the existing signalised intersection of Beenleigh Road and Bonemill Road. This will provide local access in and out of the service road to Beenleigh Road in both directions.

Project timing

Construction started in mid-November 2019 and is expected to be completed by mid-2020, weather and construction conditions permitting.

Council is committed to minimising the impact of the works on the community as much as possible and will provide further updates prior to the start of construction. Council thanks local residents in advance for their understanding during these important works to improve road safety.

Environmental impacts

Council had identified 22 street trees to be removed as part of the project. This involves removing vegetation from the verge between Beenleigh Road and the service road, as well as the eastern corner of the Nursery Avenue and Beenleigh Road intersection. To offset vegetation removal, Council is planning to plant 58 trees (45 litre equivalent) in the project vicinity and local area, in accordance with Council's policies and relevant legislative requirements.

More information

If you would like more information about this project, you can:

  • phone the project team on 1800 669 416 during business hours
  • phone Council on 07 3403 8888 outside of business hours
  • email the project team
  • write to:
    Beenleigh Road and Nursery Avenue black spot project
    City Projects
    Brisbane City Council
    GPO Box 1434
    Brisbane Qld 4001.
Last updated:26 November 2019