Temporary lane closures will be required at the intersection of Stanley Street and Moggill Road.

These closures are necessary to upgrade essential watermain infrastructure as part of the construction of the Moggill Road Corridor Upgrade project.

When will this work take place?

Half closure

This table provides information on the starting date and time of the half closure at the intersection of Stanley Street and Moggill Road.
Start Friday 19 August to Friday 2 September, weather and site conditions permitting.
Time and day Day works – Mondays to Saturdays 7am to 6pm. 

Full Closure

This table provides information on the starting date and time of the full closure at the intersection of Stanley Street and Moggill Road.
Start Early to mid-September, weather and site conditions permitting.
Time and day Day and night works – 24 hours

Where will the works be?

Works will be carried out on Stanley Street between Moggill Road and Thorpe Street/Vincent Street.

The map is north facing and shows the intersection of Moggill Road and Stanley Street at the bottom and the intersection of Vincent Street, Thorpe Street, Salisbury Street and Stanley Street at the top.
View the supporting information of the Stanley Street closure map.

What does this work include?

Construction activities will include:

  • saw cutting of the road
  • trenching and excavation to replace/install utilities
  • road reinstatement.

Traffic changes and road closures  

For the safety of all road users, there will be changed traffic conditions will be in place:

7am to 6pm between Friday 19 August to Friday 2 September.

  • Left turn lane into Stanley Street from Moggill Road will be closed to all traffic
  • Left turn lane into Moggill Road from Stanley Street will be maintained
  • Access for people walking and riding will be maintained around the work area
  • Vehicles entering Stanley Street will be detoured via Waverley Road

24 hours early to mid-September

  • Full closure of the Stanley Street at Moggill Road intersection
  • Access for people walking and riding will be maintained around the work area
  • Vehicles entering Stanley Street will be detoured via Waverley Road, vehicles and exiting Stanley Street will be detoured via Gordon Terrace    
  • Works will be incurring in the intersection between Stanley Street, Vincent Street and Thorpe Street. Traffic controllers will be on site to direct traffic through the intersection.

What does this mean for me?

  • No on-street parking will be permitted on Stanley Street between Moggill Road and the intersection of Thorpe Street and Vincent Street from Friday 19 August to mid-September. Signage will be in place and further notification will be provided to affected residents.
  • Traffic control: speed limits will be reduced in the area. Lane closures, changes to traffic flow and short-term traffic disruptions.  Traffic controllers will be on site to direct traffic.
  • Temporary lighting and lighting towers will be used to light work areas at night
  • Noise, dust and possible vibration from the construction activities. For safety reasons, reversing beepers and flashing lights will be used at all times during work hours. 

Contact us  

We thank you for your patience and cooperation during these essential works. If you have any questions, please contact the project team on: 1800 572 132 (during business hours) or email the project team

For information outside of business hours, please call Council’s Contact Centre on 07 3403 8888.

Find out more

Visit Council's website and search ‘Moggill Road Corridor Upgrade’. 

Date posted:
Last updated: 30 August 2022

Brisbane City Council acknowledges this Country and its Traditional Custodians. We pay our respects to the Elders, those who have passed into the dreaming; those here today; those of tomorrow.