Dew Street culvert replacement project | Brisbane City Council

Dew Street culvert replacement project

Brisbane City Council is pleased to announce works to replace the culvert crossing under Dew Street, opposite Wakerley Park in Runcorn are now complete.

Project summary

Address Dew Street, Runcorn
Ward  Runcorn
Project outcomes Improved flood immunity and safety of the creek crossing
Latest update End of construction

About the project

The existing Dew Street creek crossing had reached the end of its serviceable lifespan. New culverts have been installed that improve the flow capacity and safety of the crossing while minimising the environmental impact.

Works to replace the Dew Street culvert included:

  • removing the existing box culvert
  • installing two new reinforced concrete box culverts 
  • reconstructing the existing concrete path over the culvert crossing
  • landscaping works.

Timing

Construction on the project started in late May 2018 and was completed in early July 2018. 

More information

If you would like to ask questions or provide feedback about the Dew Street culvert replacement project you can:

  • phone the project team during business hours on 1800 669 416
  • phone Council on 07 3403 8888 outside of business hours
  • email the project team
  • write to:
    Dew Street culvert replacement project
    City Projects Office
    Brisbane City Council
    GPO Box 1434
    Brisbane Qld 4001
19 July 2018