Nudgee Road bridge resurfacing project - Nundah | Brisbane City Council

Nudgee Road bridge resurfacing project - Nundah

Brisbane City Council is undertaking important maintenance works to the Nudgee Road bridge at Nundah to extend the serviceable lifespan of the bridge.

Project summary

Address Nudgee Road bridge, Nundah
Ward Northgate
Project outcomes Smoother, safer driving surface and extension of bridge lifespan
Latest update Start of construction

About the project

As this bridge links major arterial roads to key industrial areas, the road receives high traffic volumes and carries heavy vehicles. This has resulted in the formation of depressions and ripples in the bridge's asphalt surface. To address this, the asphalt surface on the bridge needs to be removed and replaced.

Works will include:

  • removing the full asphalt surface of the bridge
  • installing a waterproof membrane
  • laying a new asphalt bridge surface.

Detailed traffic management plans have been developed to support these closures. Road signage, reduced speed limits and traffic controllers will be in place to redirect all bridge users along dedicated detour routes.

Download the proposed detour routes map (Word - 488kb) for more information about alternative access during construction.

Benefits

Resurfacing will provide a smoother, safer driving surface for all road users and will extend the serviceable lifespan of the bridge.

Timing

To minimise traffic delays and disruptions, works will take place over the following three consecutive weekends, weather and construction conditions permitting:

  • from 10pm on Friday 10 May to 5am on Monday 13 May 2019
  • from 10pm on Friday 17 May to 5am on Monday 20 May 2019
  • from 10pm on Friday 24 May to 5am on Monday 27 May 2019.

During these periods, construction will occur 24 hours a day.

If these dates are rescheduled due to weather or unforseen circumstances, works will take place in June 2019, weather and construction conditions permitting.

More information

For more information about the Nudgee Road bridge resurfacing project, you can:

  • phone the project team on 07 3178 0093 (during business hours)
  • phone Council on 07 3403 8888 (after hours)
  • email the project team
  • write to:
    Story Bridge depot
    Field Services
    Brisbane City Council
    GPO Box 1434
    Brisbane Qld 4001.
12 April 2019