Kangaroo Point Green Bridge construction

Brisbane City Council has appointed Connect Brisbane, led by BESIX Watpac, to design and construct the Kangaroo Point Green Bridge.

Connect Brisbane is a consortium of bridge design, engineering and construction specialists led by BESIX Watpac, who are head officed in Brisbane, and include Rizzani de Eccher, WSP, Dissing + Weitling, Blight Rayner, ASPECT Studios, Right Angle Studios and Rowland.

The consortium’s experience spans global and local projects including Perth’s signature Matagarup Bridge and Dubai’s landmark Water Canal Bridges.

Connect Brisbane will source more than 90 per cent of construction supplies and materials from South East Queensland businesses, with more than 300 local jobs and up to 50 apprenticeships created to provide a much-needed boost for our local construction industry.

As part of the project, Council will also be delivering new walking and riding connections from the bridge landing at Scott Street through to Main Street and Deakin Street in Kangaroo Point.

Construction activities are now underway for the Kangaroo Point Green Bridge, including the Main Street and Deakin Street connection, with the project expected to be completed in 2024.

Construction updates

Connect Brisbane is responsible for managing impacts related to construction of the Kangaroo Point Green Bridge and keeping the community informed for the duration of works on the project.

Council is delivering the Main Street and Deakin Street connection separate to the main bridge works carried out by Connect Brisbane.

See below for the latest construction updates for the Kangaroo Point Green Bridge, including the Main Street and Deakin Street connection.

Marine and land-based construction activities will continue at the Brisbane CBD site in December 2022 and January 2023.

Pagination

Construction animation

Watch the animation to learn about the construction of the bridge.

Construction overview

Council will work with Connect Brisbane to minimise construction impacts on the local community, where possible. While many construction activities will be undertaken from the river, work sites have been established at:

  • C.T. White Park (off Hamilton Street) and Scott Street in Kangaroo Point
  • the corner of Alice and Edward Streets, near the City Botanic Gardens in the CBD.

Initial works commenced in late 2021 and included:

  • pre-site establishment works and investigations including dilapidation surveys, locating services, noise monitoring and the establishment of an off-site fabrication yard
  • relocation of park infrastructure and utilities
  • establishment of work sites
  • diversion of pedestrian and cycle pathways, with safe access maintained through the construction areas.

Major works commenced in early 2022, with the Kangaroo Point Green Bridge expected to open to the public in 2024.

Main Street and Deakin Street connection

To facilitate construction activities for the Main Street and Deakin Street connection at Kangaroo Point, Council will establish a site compound and lay down area for materials and equipment in C.T. White Park from the week commencing 13 June 2022, weather and site conditions permitting.

The site compound will be utilised for the duration of the project, with the Main Street and Deakin Street connection expected to be complete in late 2023.

Council is committed to minimising impacts on local residents and businesses during construction of the Main Street and Deakin Street connection. For more information about these works, please contact Council’s project team on:

Construction factsheets

Download the construction factsheets to learn more about key construction activities required to build the Kangaroo Point Green Bridge.

Piling and bridge foundation construction

Project timeline

Key milestones in the development of the Kangaroo Point Green Bridge.

Stage

Late 2021

Start of initial works, including site establishment and service relocations

Stage

2022

Works in the river to construct the bridge deck, viewing areas, mast, pylons and cable stays

Stage

Mid-2022

Start of construction of the Main Street and Deakin Street connection

Stage

2023

Final fit out of bridge and landing points, including paving and landscaping

Stage

Late 2023

Construction of the Main Street and Deakin Street connection expected to be completed

2024

Construction of the Kangaroo Point Green Bridge expected to be completed

Working in the river

Connect Brisbane has established a marine construction zone to provide a safe working environment for construction of the bridge. From early 2022, marine barges will facilitate construction activities in the river.

Many of the bridge elements will be preassembled off-site and transported by water for installation, helping to reduce impacts on the local community.

A tower crane will also operate from a temporary platform in the river, close to the City side, to assist with construction of the bridge.

In consultation with Marine Safety Queensland, the speed limit in the river near the marine construction area has been reduced to six knots during construction for safety reasons.

Contact Connect Brisbane

If you have any questions or would like more information about the design and construction of the Kangaroo Point Green Bridge, you can:

Last updated: 9 September 2022

Brisbane City Council acknowledges this Country and its Traditional Custodians. We pay our respects to the Elders, those who have passed into the dreaming; those here today; those of tomorrow.