Ashgrove - Gresham Street Bridge replacement project
Brisbane City Council is replacing the existing bridge crossing at Gresham Street to ensure ongoing safety and local access for all road users.
Address | Gresham Street, Ashgrove |
---|---|
Ward | The Gap Ward |
Project outcomes | Replace existing bridge crossing to ensure safety and local access. |
Latest update |
Start of construction – April 2021 to mid-2022 You can download the:
|
About the project
Constructed in 1931, the existing Gresham Street bridge is a two-lane timber bridge with narrow pedestrian pathways. Vehicle access is restricted to 22.5 tonne which limits most large vehicles such as semi-trailers and machinery used to maintain Council roads. The bridge is now nearing the end of its serviceable life and requires replacement.
The existing bridge is also subject to flood inundation during low flood events with an immunity of between 50% and 20% Annual Exceedance Probability (AEP), being inundated once every 2 to 5 years.
The project objective is to replace the existing bridge with a new elevated concrete structure with improved 42.5 tonne load limits and flood immunity while minimising hydraulic, environmental, property and construction impacts. The new 3 span structure will be 37m in length, with a cross section total width of 13.7m to accommodate two wide traffic lanes and a 2.5m shared path on each side. The project will also upgrade the traffic lights at the Gresham Street and Waterworks Road intersection to improve the safety for all road users.
The Gresham Street bridge replacement project is jointly funded by Council and the Australian Government as part of the Bridges Renewal Program.
Temporary bridge
To facilitate the removal and replacement of the bridge in the current location, Council will construct a temporary bridge parallel to the existing structure. The temporary bridge will be a two-lane structure with a shared pedestrian and cycle path to maintain access for residents of St Johns Wood.
Project features
Project features
The project will involve:
- Construction of a temporary bridge east of the existing bridge, to maintain access during construction of the new bridge at Gresham Street
- removal of the existing timber bridge and construction of a new elevated concrete bridge
- minor relocation of the St Johns Wood Scout’s entrance to improve intersection safety
- Improved drainage infrastructure on Gresham Street and Waterworks Road
- pavement works and line marking
- upgrade to LED street lighting and traffic signals at Waterworks Road
- hard and soft landscaping, including tree planting.
Early works
Early works
Council is currently undertaking early works to relocate a number of public utility services mounted on the existing bridge to new dedicated alignments crossing under Enoggera Creek. APA Gas relocation was completed in July 2020 with Urban Utilities watermain relocation due to be completed in April 2021.
Construction
Construction
Construction for the new Gresham Street Bridge at Ashgrove will take place from mid-April 2021 and is expected to be completed by mid-2022, weather and site conditions permitting.
The majority of the construction works will be undertaken during the day and will take place between 7am and 5pm, Monday to Saturday. Certain critical components of the works will need to be undertaken at night and will generally take place between 7pm and 5am, Sunday to Thursday, when traffic volumes are lowest to ensure the safety of motorists and workers and to minimise traffic disruptions. Council will provide advance notice of out-of-hours works.
Construction impacts
During the works, residents and businesses near the bridge may at times experience increased noise, truck movements, vibration, dust and light from mobile light towers (during night works). Council will make every effort to minimise impacts to the local community and provide advance notification of particularly noisy works or out-of-hours activities.
Vibration, noise and dust monitoring will be undertaken throughout construction in accordance with the strict environmental controls to ensure the safety of the community.
Traffic changes
Temporary lane closures and detours will be required, with traffic control in place to direct road users.
During construction, temporary alignment changes to the intersection of Waterworks Road and Gresham Street will be undertaken to coincide with the temporary bridge structure. There may also be a requirement for temporary removal of the inbound kerb side T2 lane on Waterworks Road to facilitate some of the construction. Further notifications will be provided when these changes are expected to occur.
Safe pedestrian access around the worksite will be maintained at all times. Access to bus stops on Royal Parade, Gresham Street and Waterworks Road will be maintained during the works. Gresham Street and Waterworks Road will remain open to all traffic during the works however, motorists may experience some delays.
Environmental impacts
To enable these works, 71 trees within the project site boundary along Enoggera Creek have been identified for removal. Many of these are non-native or identified as weed species. As part of project rehabilitation, 103 native trees of seven different species will be planted at project completion. A further 1200m2 of shrubs will be planted in the creek and 1500m2 of grass turf will be laid near Royal Parade. All tree removal work will be carried out in accordance with the relevant environmental guidelines and Council will make every effort to minimise environmental impacts.
Project benefits
Project benefits
The project will provide:
- a 100-year design life
- improved flood immunity to the bridge deck level 5% annual exceedance probability (AEP) (1 in 20 years)
- upgrade crossing vehicle load limit from 22.5 tonne to 42.5 tonne
- improved drainage
- more reliable access to and egress from local residential area
- improved intersection safety for all road users at Gresham Street and Waterworks Road.
Project timing
Project timing
Project timings are subject to change and weather permitting:
- Detailed design – Complete
- Service relocation works – April 2020 to April 2021
- Bridge construction works – mid-April 2021 to mid-2022.
More information
If you would like to provide comments, ask questions or find out more about the Gresham Street Bridge Replacement project you can:
- contact the project team online
- call the project team on 1800 884 681
- call Council on 07 3403 8888
- email the project team
- write to:
Gresham Street Bridge Replacement project
City Projects Office
Brisbane City Council
GPO Box 1434
Brisbane Qld 4001